Solution: Parallel Courses III
Explore how to determine the shortest time to complete all courses given their prerequisite relationships and durations. Learn to model course dependencies as a directed acyclic graph and apply topological sorting to identify the earliest finish times. This lesson guides you through constructing the graph, managing in-degrees, and calculating minimum completion times, ensuring a clear understanding of dependency scheduling in coding interviews.
We'll cover the following...
Statement
You are tasked with determining the minimum time required to complete a set of courses, given their prerequisite relationships and individual durations.
There are n courses labeled from 1 to n. The prerequisite relationships between these courses are provided as a 2D integer array relations, where each entry