Solution: Parallel Courses III

Understand how to apply topological sorting to calculate the minimum time needed to complete all courses considering their prerequisite dependencies and individual durations. Learn to build a dependency graph, manage course scheduling efficiently, and evaluate the optimal completion sequence using an in-degree approach and queue processing.

Statement  

You are tasked with determining the minimum time required to complete a set of courses, given their prerequisite relationships and individual durations.

There are n courses labeled from 1 to n. The prerequisite relationships between these courses are provided as a 2D integer array relations, where each entry relations[j]=[prevCoursej,nextCoursej]\text{relations}[j] = [\text{prevCourse}_j, \text{nextCourse}_j] ...